We deliver track projects throughout the UK including works on the Infrastructure, Depots and Sidings – working as principal contractor or as a specialist track sub-contractor.

Hover or click on a project below for more information.

← All Projects

Featured Image

River Parrett Track Off / Track On

Client: Taziker Industries
Date/ Duration: Jan 2020 – May 2020
Location: River Parrett (Langport Somerset)

Scope

KGJ Price were contracted to provide Permanent Way & Civil services to Taziker Industrial to remove the track, ballast and re-instate the track at the end of a 16 day blockade during WK51 to WK53 in March 2020. Additional works included Sig

Details

TRACK REMOVAL:

o    680m of track

o    2,100m3 of ballast (to spoil)

o    588# sleepers (27# Track Panels)

o    S&T Dis-connections

 

PROGRAMME & DELIVERY:

o    2 x 12hr Core Works Shifts (672# man Hrs)

o    18# Heavy Plant Shifts

 

 

 

 

 

 

 

TRACK REPLACEMENT:

o    250m of bridge drainage

o    160m of track

o    2,100m3 of new ballast

o    588# sleepers

o    12# Welds,

o    4# Stress Welds & 700m Stressing

o    800m Tamping utilizing 2# Tampers

o    S&T Re-connections

o    ESR/TSR Design & Preparation.

 

PROGRAMME & DELIVERY:

o    6 x 12hr Shifts (2,556# man Hrs)

o    38# Heavy Plant Shifts

o    2# Conveyors