TILL Level Crossing Project

Client: Siemens
Date/ Duration: July 2020 – Decemeber 2020
Location: Tram Inn, Landovery and Llandrindod Wells

Scope

KGJ Price were contracted to provide Permanent Way Design and installation for 10 x Hollow Sleepers and 4x Pairs of IRJ’s. KGJP were then also instructed to complete the required Level Crossing deck extensions at Tram Inn and Llandrindod We

Details

Tram Inn:

o    Survey, Design and Installation of 2x Pairs of IRJ’s.

o    Installation of 2x Pairs of 4 Hole Dry IRJ’s.

o    Survey, Design and Installation of 4x Hollow Sleepers.

o    Installation of Twin Track Polysafe Deck Extensions.

o    Track CRE, Track Monitoring and CRT Management.

 

Llandovery:

o    Survey, Design and Installation of 4x Hollow Sleepers.

o    Twin Track GRP Anti-Trespass.

o    Track CRE, Track Monitoring and CRT Management.

 

 

Llandrindod Wells:

o    Survey, Design and Installation of 2x Hollow Sleepers.

o    Installation of Single Track Polysafe Deck Extensions.

o    Single Track GRP Anti-Trespass.

o    Track CRE, Track Monitoring and CRT Management.

 

PROGRAMME & DELIVERY TRAM INN:

o    1 x 27hr Core Works Shifts

o    2 x 8hr Shifts

 

PROGRAMME & DELIVERY LLANDOVERY:

o    3 x 8hr Shifts

 

PROGRAMME & DELIVERY LLANDRINDOD WELLS:

o    3 x 8hr Shifts