Case Study

RIVER PARRETT TRACK OFF / TRACK ON

August 2016 – April 2017  |  North Lincolnshire (Scunthorpe)

Client

Taziker Industries

KGJ Price were contracted to provide Permanent Way & Civil services to Taziker Industrial to remove the track, ballast and re-instate the track at the end of a 16 day blockade during WK51 to WK53 in March 2020. 

Details:

TRACK REMOVAL:

  • 680m of track
  • 2,100m3 of ballast (to spoil)
  • 588# sleepers (27# Track Panels)
  • S&T Dis-connections

 

PROGRAMME & DELIVERY:

  • 2 x 12hr Core Works Shifts (672# man Hrs)
  • 18# Heavy Plant Shifts

 

 

 

 

 

 

 TRACK REPLACEMENT:

250m of bridge drainage

  • 160m of track
  • 2,100m3 of new ballast
  • 588# sleepers
  • 12# Welds,
  • 4# Stress Welds & 700m Stressing
  • 800m Tamping utilizing 2# Tampers
  • S&T Re-connections
  • ESR/TSR Design & Preparation.

 

PROGRAMME & DELIVERY:

  •  6 x 12hr Shifts (2,556# man Hrs)
  • 38# Heavy Plant Shifts
  • 2# Conveyors