Case Study
WEM Overbridge
Oct0ber 2021 – March 2022 | WEM Overbridge
KGJ Price were contracted to provide all aspects of
Permanent Way services to Alun Griffiths to remove the
track, ballast and re-instate the track during a 101 hour
possession in Xmas 2021.
Details:
Core Elements & Scope:
- 542T of Spoil removed
• 4 x 20m Panels of Sand Filled Geocells Installed
• 230T of Ballast Installed Utilising Trimble 3D Dozer
• 420T of Top Stone Installed using auto hopper train
• 84m of Track Removed in Each Line
• 18 x 30ft Track Panels removed
• 10 x 30ft panels changed for new sleepers off the
critical path
• 126 G44’s & 17 W560 Steel Sleepers used to replace
the existing life expired Pan 9 Sleepers (84m)
• 108m of rerailing on each line
• 12 Welds Installed, 4 of which were stress welds
• 2 x Stressing Pulls totalling approx. 600yards carried
out in short midweek night possessions (4 Hours
working time)
• Approx. 400m of tamping carried per line
• All Track and spoil removed in less than less than 9
hours and handed over to Civils on schedule
• Full Installation scope completed and right time
hand-back despite severe slippage to civils installation
program
• Quick mobilisation to provide additional resource and
reprogramming following civils program slippage
• Comprehensive dilapidation survey carried out to
note down pre-existing issues with Pan9 Baseplates
Ask Us Anything. Anytime.
For more details about our projects and capabilities please don’t hesitate to get in touch with us.
- KGJ Price Rail Limited, Unit 1A, Kellingley Road, Weeland Park, Knottingley, WF11 8DS
- railenquiries@kgjpricerail.co.uk
- 0333 7722421