I bet a lot of you are wondering what happened to the crossover we posted a video of a few weeks ago? Well its now safely in its final home just outside Euston sat on its very own new bridge! Its been a long few days over Xmas with plenty of challenges to keep our guys on their toes but we all pulled together alongside our good client Story to deliver the works fully welded, fully stressed and back at linespeed on the core. I hope that crossover wasn’t scared of heights! 😮

Summary of KGJ’s works (in part supported by our trusted supply chain):
Supply & Installation of CVs 9.25 Modular Crossover inc 6 x Plain Line Panels
HW2000 Plug Coupler Upgrades
S&T Disconnections, Reconnections & Testing
Points Heating Disconnections, Reconnections & Testing
36 Welds inc 2 x Level 3 Stressing Pulls
600m of design tamping
CRE Support – PWay, S&T & E&P
Program & Planning Support
Track Monitoring
CRT
📩 RailEnquiries@kgjpricerail.co.uk
☎️ 0333 7722421
🌐 www.kgjpricerail.co.uk


More Posts

Christmas Follow Up Tamp

Team KGJ were back down Camden for the follow up tamp on our Xmas works. While we were there we also took the opportunity of

2076 Modular Crossover Inspection

Sorry for the like of content the last few weeks, we’ve been busy getting ready for our Christmas works and also busy installing UTX’s, URX’s

Midweek 28

Another Busy & Productive week for one of Many KGJ Price Rail Ltd Lineside Civil’s Teams out on site this week during Midweek 28. SMIO Concrete pour

Send Us A Message

What are you looking for?