Existing Modular S&C Unit – Removed and Reinstated

KGJ Price Rail Ltd specialise in CRT Management & Track Monitoring, inline with NR/L2/CIV/177 (Issue 02).

Also Re-installed the Modular S&C to a higher standard rectifying existing gauge issues within the Modular Shroud area through detailed knowledge of the Modular S&C System. During the Core Renewal, below are just some of the key items carried out:

  • 2200T of Ballast Installed Utilising Trimble 3D Dozer
  • 84m of Existing CWR Removed & Reinstated, 11 x 18288mm Closure Rails & 108m of New CWR Installed
  • 18 PEMs & 12 LEMs Used to Lift out and Reinstall a Modular CEN56v EVs 1 in 15 Turnout
  • 129 G44’s Removed & Reinstated + an additional 169 New G44’s installed
    43 Welds Installed, 10 of which were stress welds & x2 to set the ball & claw
  • 5 Stressing Pulls in & around the S&C Totalling 626 Yards
  • Approx 1600m of tamping carried out over all lines disturbed, including 9 S&C Units
  • All Track removed in less than 24 hours & handed over to Civils ahead of schedule
  • Full Installation scope complete 4hr ahead of schedule
    Innovative & Bespoke Track Monitoring Solution Provided due to the EPS Block Back Fill associated with the bridge construction.
  • Constant Programme revisions throughout due to Site challenges.

More Posts

Christmas Follow Up Tamp

Team KGJ were back down Camden for the follow up tamp on our Xmas works. While we were there we also took the opportunity of

Christmas Works

I bet a lot of you are wondering what happened to the crossover we posted a video of a few weeks ago? Well its now

2076 Modular Crossover Inspection

Sorry for the like of content the last few weeks, we’ve been busy getting ready for our Christmas works and also busy installing UTX’s, URX’s

Send Us A Message

What are you looking for?