Track Handback & “Medium Risk” Track Monitoring Complete WK46, Saturday & Sunday Days at Clacton on Sea whilst Our Client undertook Movac Driven Pile Installations (x4) & Pre Cast Base Installation Works (x1). Pre & Post Monitoring was also carried out at each site.
Following Completion of works, Joint Gap Surveys took place along with Calculation of JCT & CRT (W) Values in Jointed Track.
So far this week, All Sites Remain Stable with No issues to report.