Team KGJ Price Rail Ltd had yet another Productive Weekend at Nether Poppleton Level Crossing in York During Weekend 13 on Sunday Night’s ROR Possession. Works Successfully Delivered to Programme & Handed Back to Traffic on Time as per the Tasks Listed Below: – 🔹 Installation of ZO, ZN, YO & YN Corner RTL Buried Post’s 🔹 100m of Lineside Cable Route Installation 🔹 100m Devegetation Works & Removal/Reinstate Vortok Fencing 🔹 211m Trough Route Removal & Install cables into the New Route 🔹 Pile Installations “P100 & P101” Inclusive of Trial Holes, Baseline Survey & Post Install Track Monitoring “Medium Risk” 🔹 Material Deliveries of Signal Laydown Area Materials, SPT Materials, Telecoms Bases & Hardstands, Delivery of Remaining Cable Route. Great Work everyone Once Again! 👏👏👏👏 📩 RailEnquiries@kgjpricerail.co.uk ☎️ 01724 858125 🌐 www.kgjpricerail.co.uk #LevelCrossingUpgrades #KGJPRailLTD…more