- Circa 300m of De-Vegetation complete during midweek 36 for our client in the York area.
- All planned works complete in readiness for trail trench excavation works.
- KGJ Price Rail Ltd Lineside Civils Team will be installing the GSM- R Mast Base in the New Year.